Site Remediation

Client
GCDA
Location
Tugun, QLD
Contaminants
- Landfill waste
- Asbestos
Remediation of landfill for infrastructure works
Overview
Remediation of zones through a former landfill so as to establish a safe workplace for contractors to construct pipe network and other services for the desalination plant. Two major service trenches were excavated to specific design levels and contaminated spoil was transported and disposed offsite to landfill.
All contaminated material was managed in accordance with EPA requirements and asbestos supervision and controls were implemented as required throughout the project. Continuous dewatering was undertaken throughout the excavation works to allow excavation to design levels and contaminated water was treated and disposed to sewer under trade waste. A number of live services, including water, sewer, electrical, telecommunications and stormwater were encountered during excavation works which required removal and/or diversion and re-instillation to allow excavation works to proceed. This included the removal and replacement of a live section of sewer rising main. Upon completion of excavation works a geofabric marker was installed to the trench profile and trenches were backfilled under AS1 geotechnical supervision.
Summary
- Excavation of service trenches through a former landfill to specific design requirements
- Transport and offsite disposal of approximately 10,000m3 of contaminated soil generated from the excavation of the service trenches
- Contaminated materials management throughout the duration of the excavation works including materials tracking and asbestos management
- Location, removal and/or diversion and re-instillation of a number of services (water, sewer and stormwater) to allow continuous excavation of the service trenches. This included the removal and replacement of a live section of sewer rising main.
- Continuous dewatering throughout the excavation works, treatment and disposal of contaminated water to sewer under a trade waste agreement
- Installation of geofabric marker layer to trench profile
- Controlled backfilling of service trenches with engineered fill under AS1 geotechnical supervision

Client
BCD Technologies
Location
Narangba, QLD
BCD Technologies Construction Works, Narangba QLD
Overview
Enviropacific were contracted by BCD Technologies to manage the civil and construction works for the upgrade of the onsite Water Treatment Plant and recently acquired thermal desorption unit. Enviropacific managed the constructions works in accordance with the approved design and value added in the supply chain for the execution of the works.
All works completed were inspected and approved by an independent engineer. Civil earthworks involved cutting the formation to the design level and excavating, stockpiling and storing soils for future remediation works. Enviropacific managed the installation of 52 timber piles beneath the water treatment slab, construction of lower reinforced concrete slab for the water treatment plant and the installation of retaining walls for split level of works. Enviropacific also executed the installation of upper concrete reinforced slab for the direct fired desorption plant. Enviropacific managed the installation of eight storage tanks and plumbing works for the waste effluent treatment system and storm water management system.
Summary
- Excavation earthworks.
- Installation of 52 timber piles.
- Construction of reinforced concrete slabs.
- Construction of block work retaining walls.
- Backfilling behind retaining walls.
- Water Treatment Plant equipment installation.

Client
Orica Australia
Location
Kooragang Island, NSW
Contaminants
- Arsenic
Immobilisation of Arsenic at the Orica Ammonium Nitrate Facility
Overview
Remediation of the Orica ammonium nitrate facility on Kooragang Island involved treatment of approximately 7,000 tonnes of arsenic impacted soil and concrete, using a chemical fixation and solidification approach that involved formation of iron arsenate. The contaminated waste was immobilised under a DECC Specific Immobilisation Approval, and disposed of to a licensed landfill.
Summary
- Excavation of remediation areas to stockpile.
- Onsite treatment of approximately 7,000 tonnes of soil using a chemical fixation and solidification approach.
- Application to the DECC for an Immobilisation Approval for the treated waste.
- Disposal of approximately 7,000 tonnes of treated contaminated waste as Solid Waste to a licensed landfill.
- Installation of sheet piling system to delineate excavation areas to reduce excavation quantities.
- Extensive site re-instatement works including the importation and placement of over 10,000tonne of clean backfill material and associated re-vegetation works

Client
VicTrack
Location
Spotswood, VIC
Contaminants
- Arsenic
- PAHs
- Asbestos
Victrack Spotswood Railyard Remediation and Civil Works
Overview
Works are nearing completion and have involved the demolition and removal of existing rail infrastructure, excavation and treatment, under approvals from EPA Victoria, of approx 10,000 tonne of Arsenic and PAH contaminated soil to facilitate encapsulation in on-site cell. Following validation of the site Enviropacific will complete civil works for the future distribution facility including stormwater drainage, access road and 20,000m2 of car park sub-base.
Summary
- Demolition of rail infrastructure and buildings
- Obtain EPA approvals for on-site treatment of Arsenic contaminated soil
- Chemical fixation of Arsenic contaminated soils to meet EPA approval and facilitate on-site encapsulation in purpose built cell
- Excavation and construction of 10,000m3 containment cell with secondary leachate collection system
- Placement and compaction of approx 10,000m3 of contaminated soils into cell
- Civil works for future distribution facility including stormwater drainage, access road and sub-base for car park.

Client
Daracon (Bovis Lend Lease Project)
Location
Charlestown, NSW
Contaminants
- PAH
- Lead
- Asbestos
- Arsenic
Excavation and remediation for construction of Charlestown extensions
Overview
Project involved all bulk and detail excavation and remediation works to enable the construction of the new extension of the Charlestown Square Shopping Centre, The New Charlestown Bowling Club, Kahibah Child Care Centre, St Johns Sport Field and all road works required for the construction.
Summary
- Disconnection of existing services and removal of redundant underground stormwater and sewer service
- Strip to stockpile 6,500 m3 of topsoil.
- Excavate, segregate, cart, spread for re-use in a different site and compact 20,000 M3 of inert/VENM soil.
- Excavate and dispose of 4,000m3 of Asbestos impacted Soil.
- Cut to fill 30,000m3 of Asbestos Impacted soil followed by capping with marker layer and 6,000m3 of engineered clay cap.
- Chase and excavate to stockpile 850m3 of slag impacted soil.
- Construction of on-site slag encapsulation cell including the supply and installation of GCL layer.
- Bulk excavation, batters and sub grade trimming to accommodate all roads, basements, car parks and ground slabs.
- Detail excavation required for the installation of new services, pile caps and foundations required for the construction.

Client
Delfin Lend Lease
Location
St Marys, NSW
Former ADI Site Remediation – St Marys
Overview
The ADI Site was a former Commonwealth Government Business entity that used the property as a munitions factory from 1940 up until its closure in 1993. Residential development commenced in 2004 with Enviropacific conducting ongoing remediation works on future residential stages.
Summary
- Remediation of asbestos contaminated soils in various areas and removal of AC conduits.
- Remediation of PCB contaminated soils
- Removal of SMF encased piping under former rail bridge.
- Removal and remediation of redundant service infrastructure including sewers, stormwater pipes, and signal cables. Care was taken around all sewer lines due to the possibility of traces of TNT and RDX. Implementation of GPS Materials Tracking System for removal of all removed infrastructure.
- Enviropacific worked closely with UXO contractor Gtek during remediation to assess for unexploded ordinances. All remediated areas were subsequently approved for residential development with site auditor sign off under NEPM A guidelines.
- Sourcing and management of the importation of 20 000m3 of fill

Client
MacCormick Civil and Tunnelling
Location
Warriewood, NSW
Contaminants
- Acid Sulfate soils
- Acidic Groundwater
Acid Sulfate soil and water treatment during the Narrabeen creek sewer installation
Overview
The works involved the treatment of groundwater for turbidity and pH and subsequent discharge to land. Liming of acid sulphate soils from spoil created from the excavation of the manholes, and subsequent disposal to landfill.Summary
- Neutralisation of acid sulphate soils using agricultural lime.
- Offsite disposal of treated soils as general solid waste
- Treatment of groundwater by addition of a coagulant and flocculent to reduce the turbidity below 30 NTU
- Addition of a caustic (sodium hydroxide) to ensure pH is between 6.5 and 9 prior to discharge
- Controlled Discharge of water to nearby field

Client
Baulderstone Pty Ltd
Location
Sydney Airport, NSW
Treatment of acid sulphate soils at Sydney airport
Overview
The contract works involve the treatment and management of approximately 12,000 tonnes of acid sulphate soils and potential acid sulphate soil excavated as part of Runway 25 - Runway End Safety Area project for Baulderstone Pty Ltd.
Summary
- Treatment of ASS and PASS by addition and mixing of liquid lime.
- Sampling and lab testing of treated soils to confirm successful treatment.
- Management of soil during and after treatment to strict airport environmental and operational requirements.
- Management and treatment of rainfall runoff potentially acid affected.

Client
Armidale Dumaresq Council and West End Market Place
Location
Armidale, NSW
Contaminants
- PAH
- Phenol
- Asbestos
- Coal tar
Remediation of the former Armidale Gasworks Site
Overview
This project involved the remediation of the former Armidale gasworks site required to enable construction of the future West End Market Place in Armidale, NSW. The site area is approximately 1.7 ha.
Summary
- Installation and maintenance of erosion and sediment control measures
- Disconnection of existing services and demolition and removal of former gasworks infrastructure
- Demolition and removal of redundant underground stormwater, gas and sewer services
- Excavate, segregate and stockpile of approx. 25,000 tonnes of Inert, Solid, Industrial and Hazardous waste
- Conduct Hazardous waste treatment trial
- Remediation of contaminated soils therein including treatment of 15,000 tonnes of coal tar impacted soils
- Design, supply, install and operate water treatment unit to treat 400 km3 of contaminated underground water prior dispose to sewer
- Construction of 8 m vertical barrier wall around perimeter of 1.7 ha former Armidale gasworks site, barrier layer, GCL, drainage layer, gas vents and monitoring wells
- Supply and placement of engineered base materials across site
- Excavation, treated timber piles, steel and concrete to pile caps, stripfootings, loading deck and all foundations for the West End Market Place

Client
ACTNOWaste
Location
West Belconnen Landfill, ACT
Contaminants
Total Petroleum Hydrocarbons
Bioremediation of sullage material – West Belconnen landfill
Overview
The works involve the removal of approximately 1800m3 of sullage material contained in one of the sludge ponds and bioremediation (onsite) over a two and a half year period. The sullage material includes a mixture grease trap waste, oily liquid and fatty wastes. The works also include capping of the sludge and dewatering pond areas subsequent to removal of the sullage waste and capping of the windrow area following completion of the bioremediation.Summary
- Establishment of groundwater wells and a monitoring program.
- Removal of the sullage waste from pond 5, mixing with green waste and formation of windrows.
- Installation of a clay cap, topsoil and dryland grass over the empty pond areas.
- Regular monitoring and turning of the windrows.
- Completion of bioremediation and re-use of material onsite.
- Installation of a clay cap, topsoil and dryland grass over the windrow area.

Client
Albury City Council
Location
Albury, VIC
Contaminants
THP - in excess of 150,000mg/kg
Remediation and Rehabilitation of Wirlinga Liquid Waste Facility
Overview
Remediation and rehabilitation of Wirlinga Liquid Waste Facility, Albury NSW. The works involved the extraction, pre-treatment and off-site disposal of TPH impacted waste water, excavation and treatment of approx 7000m3 of sludge and sediments resulting from the former liquid waste facility.
Sludge and sediments were bioremediated on site over a 6 month period to concentrations that allowed off-site disposal to the local landfill.
Summary
- Pre treatment of liquid waste prior to off-site disposal
- Excavation and bioremediation of sludge’s and sediments
- Nutrient and green waste addition and mixing utilising a soil recycler (Retera)
- Transport and stockpiling into windrows
- Off-site disposal

Client
Dept. of Justice
Location
Southbank
Contaminants
- Petroleum Hydrocarbons
- Chlorinated Hydrocarbons
- Heavy Metals
Remediation of State Coronial Services Centre
Overview
petroleum HYDROCARBON, lead, chlorinated hydrocarbon impacted soil Enviropacific are currently undertaking the remediation of the State Coronial Services Centre for the Department of Justice in inner Melbourne. The volatile and odorous nature of the contaminants, combined with the close proximity of sensitive receptors has required the construction of an Odour Control Structure to encompass the excavations. An air extraction and treatment system ensures no adverse impact to the ambient air quality. Excavations are being completed to below groundwater levels and a water treatment plant has been established to treat leachate prior to disposal under a Trade Waste Agreement with South East Water.Summary
- Highly odorous and volatile contaminants
- Establishment of Odour Control Structure & Air extraction / treatment system
- Development & implementation of detailed management plans
- Stringent air monitoring programme
- Treatment of Category A soil to allow offsite disposal
- Classification and offsite disposal EPA licensed landfill

Client
Nyrstar
Location
Hobart
Contaminants
- Arsenic
- Cadmium
- Lead
- Mercury
- Selenium
Chemical Fixation of Manufacturing Waste
Overview
Enviropacific are currently undertaking the chemical fixation of manufacturing waste containing high concentrations of arsenic, cadmium, lead, mercury, selenium to facilitate disposal to an EPA licensed landfill as level 2 waste. The works are being conducted on an operational smelting facility in accordance with EPA approvals which include the requirement for stringent environmental and safety controls to eliminate any impact on the surrounding workers and environment. Enviropacific are contracted to manage and treat in excess of 6,000 drums of mercury filter cake, 400 tonnes of sulphuric acid sludge, 200 tonnes of mercury contaminated bricks and other wastes identified during the works. Enviropacific have undertaken extensive treatment trials to ensure a successful treatment outcome while minimising reagent addition and bulking. To enable optimum treatment Enviropacific have employed our hand held XRF unit to provide real-time assessment of contaminant concentrations in each treatment batch as well as to identify historic drum contents. With safety always a high priority Enviropacific procured a custom-built rotating drum grapple for handling and emptying of the drums thereby minimising worker exposure to contaminated materials and mitigating manual handling risks. The chemical immobilisation treatment process generally involves pre-mixing the contaminated materials with a filler agent for liquid adsorption to produce a spadeable product for treatment processing. The pre-mixing is undertaken in Enviropacific’s portable All-Shelter for dust and odour control. Subsequent to the pre-mixing, the contaminated materials will be chemically immobilised through the stoichiometric addition of treatment reagents and high shear mixing in the Enviropacific Hitachi Pugmill.Summary
- Identification and sorting of historical waste utilising our hand held XRF device
- Establishment of environmental and safety controls
- Transportation to treatment area and emptying of over 6000 drums of waste using purpose built rotating drum grapple
- Addition of chemical reagents and high shear mixing with Hitachi pugmill to chemical immobilise the contaminants
- Conformance sampling of waste to ensure leachable concentrations are less than the level 2 criteria
- Disposal of waste to EPA licensed landfill cell





